User Story #28 (closed)
Opened 18 years ago
Closed 14 years ago
Externalize Util Package
Reported by: | anonymous | Owned by: | cxallan |
---|---|---|---|
Priority: | major | Milestone: | OMERO-Beta4.2 |
Component: | Bin-Services | Keywords: | n.a. |
Cc: | Story Points: | n.a. | |
Sprint: | n.a. | Importance: | n.a. |
Total Remaining Time: | n.a. | Estimated Remaining Time: | n.a. |
Description
The rendering util package needs to be externalized (and added as a dependency) so that it can be used by Shoola.
Change History (10)
comment:1 Changed 18 years ago by anonymous
- Keywords iteration1 added
comment:2 Changed 18 years ago by cxallan
- Keywords iteration2 added; iteration1 removed
comment:3 Changed 18 years ago by cxallan
- Keywords iteration3 added; iteration2 removed
comment:4 Changed 18 years ago by cxallan
- Keywords iteration3 removed
- Milestone changed from 3.0-M2 to 3.0-M3
- Version set to 3.0-M3
comment:5 Changed 18 years ago by cxallan
- Keywords iteration4 added
Assigning this for completion with the ThumbnailService.
comment:6 Changed 18 years ago by cxallan
- Keywords iteration5 added; iteration4 removed
Moving to iteration5.
comment:7 Changed 17 years ago by cxallan
- Keywords iteration5 removed
- Milestone changed from 3.0-M3 to Future
- Status changed from new to assigned
Plopping this into the "Future" milestone.
comment:8 Changed 15 years ago by cxallan
- Milestone changed from Unscheduled to OMERO-Beta4.1
- Version 3.0-M3 deleted
comment:9 Changed 15 years ago by cxallan
- Milestone changed from OMERO-Beta4.1 to OMERO-Beta4.2
comment:10 Changed 14 years ago by cxallan
- Resolution set to worksforme
- Status changed from assigned to closed
Much of this has been completed. Re-open as necessary.
Note: See
TracTickets for help on using
tickets.
You may also have a look at Agilo extensions to the ticket.
Delegating this to milestone 3.